otley bridge pedestrian safety

Leeds City Council is planning essential repairs on Otley Bridge, with options including a single lane for traffic or a temporary footbridge, despite concerns about tree felling. The project is set to begin in March 2025, aiming to enhance pedestrian safety while balancing community and environmental interests.

What are the proposed solutions for the essential repairs on Otley Bridge?

The proposed solutions for Otley Bridge repairs include reducing traffic to a single lane for pedestrian safety during construction, or installing a temporary footbridge. The latter option, preferred by Leeds City Council, faces environmental concerns over the potential felling of trees but aims to minimize traffic congestion and ensure public safety.

Transport Implications and Pedestrian Safety

Leeds City Council has made pedestrian safety a paramount concern, especially in relation to the condition of Otley Bridge. The bridge, serving as a vital conduit for traffic and pedestrians alike, has reached a critical juncture where essential repairs can no longer be deferred. Two primary options are currently under consideration to facilitate these repairs. One is to reduce Otley Bridge to single lane traffic, aiding pedestrian crossing during the construction period. The other, more contentious option, involves the installation of a temporary footbridge.

Councillor Jonathan Pryor, the council’s deputy leader and executive member for economy, transport and sustainable development, underscored the dilemma: “We recognize the strength of feeling from certain local community groups against the felling of the trees.” He further emphasized, “However, public safety has to be our main priority, and the essential replacement work to the footbridge will not be delayed regardless of the outcome for the trees.”

Given the impending annual swimming event in the River Wharfe on New Year’s Day, the council has announced the closure of the pedestrian footway for the event’s duration and until 3 January 2025. This allows for further in-depth inspections. As a result, traffic on Otley Bridge will be reduced to a single lane with temporary traffic lights in place to facilitate pedestrian crossing. Road users should anticipate possible delays as this arrangement is expected to increase journey times.

Environmental Concerns and Community Response

The temporary bridge proposition, while practical, has sparked controversy due to its environmental implications. Specifically, it would require the felling of two nearby trees, causing unrest among community groups and environmental activists. In light of the uproar, Leeds City Council has taken a step back: no further action will be taken in regard to the oak tree or the other trees before Monday 6 January 2025 at the earliest. This hiatus is an acknowledgment of the community sentiment and an opportunity for further review and consultation.

Responding to these concerns, Councillor Pryor appreciates the community’s patience: “We would also like to thank residents for their patience and understanding during the temporary closure of the footway for the New Year’s Day annual swim event.” He speaks to a broader council commitment to engaging with the public and valuing their input on local matters.

Critically, the need for a temporary footbridge is still being defended by the council as the preferred approach. This is due to the substantial effects that 3-way temporary traffic lights would pose over an extended period. These effects include significant vehicle queues, increased air pollution, pedestrian safety risks, congestion in the town center, and potential negative impacts on local businesses. The council plans to address the loss of the trees by planting a minimum of 13 semi-mature trees across Otley, with locations such as Tittybottle Park being considered, pending community consultation.

Project Timelines and Future Steps

The council has outlined a provisional timeline for the footbridge works. Installation of the temporary footbridge is scheduled to begin in March and last approximately 12 weeks, with the bridge expected to open in spring 2025. Subsequently, the removal of the existing footbridge will commence in spring 2025, with the work anticipated to continue for around 20 weeks. The unveiling of the new permanent footbridge is slated for autumn 2025.

These dates, however, remain contingent upon factors such as weather, river conditions, and the structural assessment of Otley Bridge after the removal of the existing footway. The council has committed to keeping the local communities and key stakeholders informed with further details about the replacement works and their associated timelines.

For those seeking more information or wishing to voice their opinions, the council has established a dedicated platform for public discourse and updates. Interested parties can visit Have Your Say Today – Otley Bridge – Commonplace to engage with the project, ask questions, and submit feedback.

The Otley Bridge project represents a complex interplay of transport needs, environmental stewardship, and community engagement. As the situation evolves, Leeds City Council remains dedicated to striking a balance that prioritizes public safety while respecting both the natural environment and the sentiments of the local populace.

  • Leeds City Council plans to begin essential repairs on Otley Bridge in March 2025, focusing on pedestrian safety and environmental considerations.
  • Proposed solutions include reducing traffic to a single lane or installing a temporary footbridge, with the latter facing opposition due to tree felling concerns.
  • The council will temporarily close the pedestrian footway for the New Year’s Day swimming event until January 3, 2025, reducing traffic to a single lane with temporary lights.
  • Community response to the temporary footbridge has led the council to pause action on tree felling until at least January 6, 2025, acknowledging local concerns.
  • The project timeline includes 12 weeks for the temporary footbridge installation and an expected opening of the new permanent footbridge in autumn 2025, subject to various external factors.